News

AUTOCESTE FBIH: REMEDY OF DEFECTS OF FIELD 4 COMPLETED, REPAIRS WILL BEGIN SOON ON REMAINING AFFECTED PARTS OF SPANNING STRUCTURE



SARAJEVO, FEBRUARY 7 (ONASA) – Autoceste FBiH announced that work is underway to repair cracks on the Počitelj bridge.
As they said, the elimination of defects in field 4 has been completed, and soon they will continue with the elimination of defects in the remaining affected parts of the span structure.
The bottom plate on the Počitelj bridge that broke last year was repaired, the opening is expected before the summer
“Thus, the bridge returns to its designed state, which means that it will have the same load capacity, usability and durability as provided for in the main project,” announced Autocesta FBiH.
In parallel with the works to eliminate defects, preparations are being made for the installation of fences, transitional devices, and preparations for the execution of the remaining finishing works.
“According to the predicted dynamics, these works should be completed in just a few months, and the complete bridge by the beginning of the summer season,” they concluded.
Cracks were noticed last summer on the Počitelj bridge, which is being built as part of Corridor 5C.